Join - Funding Requirements (Non-Michigan Hospitals)

Resources Required / Non-Michigan Hospitals

There is currently no fee to join MPOG. During the implementation phase (~6 months) sites should allocate clinical, IT and project management resources. These resources will be necessary whether you plan to participate in the research or quality improvement missions of MPOG. Based on previous experience we recommend that a clinical resource is allocated at approximately 0.4 FTE during implementation and 0.2 FTE once the extract is completed and a site is live. Clinical resources can include clinical research coordinator, quality improvement nurse, CRNA, or anesthesiologist.

The anesthesia information management system that you have in your hospital can affect the resources required for implementation. We have worked with Epic to build an extract from Epic to MPOG that you can install at your site with the help of your Epic Technical Services (TS) representative. We also have significant experience with GE Centricity and Cerner. For other anesthesia systems, a site will have to rely on their IT team to build an extract to MPOG and plan on devoting an extra 2.5x the development effort (75%).

Estimated FTE Requirements to for MPOG Implementation:

 
Clinical Team
Development Team
Project Management
Implementation of Interface (6 months)
40%
30-75%
5%
Maintenance
20%
5%
0%

Estimated software/ hardware costs:

Computer Equipment and SoftwareEstimated Costs
Microsoft SQL server 2012 site license or newer$5,000
SQL Server 2012 Local Database and Virtual Machine$8,000
Application Server - Internal$4,000
Application Server - DMZ$4,000

If you are a hospital located in the State of Michigan hospital you may be eligible to receive funding from Blue Cross Blue Shield Michigan.  For more information on funding opportunities and application deadlines, please see the Michigan Hospitals page.